First phase groundworks Bracknell

First phase groundworks complete at Bracknell.

Nicola Esson Construction News

First phase groundworks are now complete at Bracknell. With ground bearing waterproof slab, lift pits and retaining walls all completed, the area is ready for bricklayers and steel erectors. Work now starts on installing the drainage outside of the building footprint and a large soakaway tank to the rear of the site.